TeamBoard ProScheduler

View settings

The View Settings allow you to customize how the timeline is displayed to suit your preferences. Below is a detailed table explaining each setting in the View Settings:

CleanShot 2026-01-16 at 13.30.33@2x-20260116-063101.jpg

View settings

How it works

Show completed tickets: When enabled, tasks marked as completed are displayed on the timeline.

CleanShot 2026-01-16 at 13.34.18@2x-20260116-063453.jpg

Detailed Scheduling: When enabled, you can open a Planning Dialog to schedule tasks and adjust all scheduling details in one place.

CleanShot 2026-01-16 at 13.35.46@2x-20260116-063559.jpg

Show Project duration: Displays the overall time span of a project.

  • Gantt view: Shows a single project-level bar spanning from the earliest start date to the latest end date.

  • List view: Displays the project’s start date, end date, and total duration as a summary.

CleanShot 2026-01-16 at 13.36.49@2x-20260116-063945.jpg

Column divider: When enabled, a visual divider is added between columns in the table for better organization.

CleanShot 2025-09-21 at 20.51.18@2x-20250921-154744.jpg

Show all plans: When enabled, every scheduled plan linked to a work item is displayed on the timeline, instead of only showing the main task bar.

CleanShot 2026-01-16 at 13.48.26@2x-20260116-064901.jpg

Work item summary: When enabled, the work item summary is shown on Gantt bars. You can position it on the left, right, inside, or hide it.

CleanShot 2026-01-16 at 13.51.48-20260116-065206.gif

Highlight day off: When enabled, days off such as weekends or holidays are highlighted in gray on the timeline.

CleanShot 2026-01-16 at 15.34.29@2x-20260116-083518.jpg

Mark non-working days: When enabled, non-working days such as weekends or holidays are marked on the Gantt bar for clarity.

CleanShot 2026-01-16 at 15.33.13@2x-20260116-083349.jpg

Show work item key: When enabled, the unique identifier (work item key) for each task or ticket is displayed on the timeline.

CleanShot 2026-01-16 at 15.39.03@2x-20260116-084002.jpg

Show detailed tooltip: When enabled, a tooltip with details about the task is displayed when hovering over a task.

CleanShot 2026-01-16 at 15.41.07@2x-20260116-084215.jpg

Show progress: When enabled, a progress bar is displayed on tasks, helping users track completion status.

CleanShot 2026-01-16 at 15.51.11@2x-20260116-085211.jpg

Show duration: When enabled, the total scheduled duration of each task is displayed on the timeline.

CleanShot 2026-01-16 at 15.49.44@2x-20260116-085026.jpg

Show work item overdue: When enabled, overdue tasks are marked with warning , making it easy to spot delays and take corrective action.

CleanShot 2026-01-16 at 15.47.55@2x-20260116-084856.jpg

Show weekend days: When enabled, the calendar view includes weekends, shown as gray columns in the timeline for a more focused work schedule.

CleanShot 2026-01-16 at 15.46.20@2x-20260116-084654.jpg

Show assignee: When enabled, the assignee is displayed next to the Gantt bar for easy identification.

CleanShot 2026-01-16 at 15.43.11@2x-20260116-084326.jpg