Gantt settings

Only Jira Admins and App Admins can configure Gantt settings.

TeamBoard ProScheduler allows you to map out dependencies between tasks. This feature is seamlessly integrated with Jira work item links.

Accessing Gantt settings

  1. Click on ⚙️ Settings from the sidebar.

  2. Select Gantt to open the Gantt settings.

Accessing Gantt settings.jpg

The app supports four types of task dependencies to help manage and visualize task relationships within the Gantt chart.

Dependency type

Description

Start-to-Finish

A task cannot finish until another task starts

Start-to-Start

A task cannot start until another task starts

Finish-to-Start

A task cannot start until another task finishes

Finish-to-Finish

A task cannot finish until another task finishes